Case Study

The solution to sensitive situations.

After conducting a fix for a burst pipe on the hot water line at the Arts Centre Melbourne, it was assessed that the internal pipe corrosion was worse than expected. Arts Centre asked us to immediately conduct sampling to assess the remaining hot water lines throughout the building.

The Problem:

The Australian Ballet School were in-house with the Australian Opera to follow. They couldn’t have any interruptions to the supply of hot water during the day or night, or the Arts Centre ran the risk of damages costs due to having no amenities.

The Arts centre has a series of 6 clarifiers throughout the building, which work simultaneously to heat the water as it circulates the building. We weren’t sure if the system would hold up with one clarifier down for the samples to be taken until we conducted a midnight test.

The Solution:

We engaged and worked with a liquid nitrogen freezing company to strategically shut down the clarifiers at night. It takes the clarifiers approximately 1 day to cool down before we could freeze the lines, take the pipe sample, re-connect the pipe and move to the next unit.

The Outcome:

All 6 samples were successfully taken from the clarifier system of copper pipe ranging from 32mm – 100mm without any interruption to the water supply during the 5 day period the samples were taken.

Contact Us
Head Office:
3-4/177 Beavers Road
Northcote VIC 3070
Gippsland Office:
20 Pearse Street
Warragul VIC 3820
Keysborough Office
38 Atlantic Drive
Keysborough VIC 3173
Perth Office:
43 Nicholas Crescent
Hilton WA 6163
Plumbing and Civil :  1300 677 669
Metering: 1300 994 559
After Hours: 1300 677 669
cross-circle